Freedom of Speech Denied. (What we recently encountered, and how we handled it.)
We have been writing a bi-monthly article for a large cost data magazine for a bout six months now. We recently wrote one that compared that publishers cost data with another large cost data company. We didn’t disparage either company, we simply pointed out the best features to use for each and explained the reasons why. The publisher of the magazine we were writing for called me and expressed his disdain for our article; citing that we did not do enough to promote his cost data. I explained to him that we didn’t say anything negative but just steered people away from its weaknesses and towards it’s strengths. This publisher didn’t like this and felt that his competitors cost database was cast in a more favorable light than his own.
We respectfully disagreed but sent our article to several
other professionals in our field to review. They agreed that nothing negative
was said. We were given a choice - revise the article or it would not be
printed. We politely declined. This publisher, like many, was disallowing
freedom of speech and was attempting to control whatever narrative he was
trying to promote. Not cool. Freedom of speech should be allowed on all
platforms. So, we informed the magazine that we would no longer be writing for
them. It’s disappointing to run into this. We inadvertently insulted someone’s
baby/creation, and despite providing constructive criticism as to why their
product was viewed as sub-par by the people he was specifically marketing to,
he did not want to hear it.
So here we are, and here is the article, published
here:
Cost Databases
When we venture out across the nation or online to teach
estimating, the number one item that comes up for discussion and sometimes a
heated debate is the subject of cost databases. We hear statements such as
“that system is useless” and “that company is never accurate” and “we simply
cannot rely on them”. It’s rare that we hear something positive said about
these various databases. The database sources are published by multiple
companies including the company this article was written for. While it is easy
to jump on the hate bandwagon, we really have to take a moment and evaluate
these comments.
So, can these databases be trusted? We think they can, in
certain cases, with the right amount of industry knowledge and vetting.
Nothing is perfect, nothing is exact…which is why it’s referred to as
estimating, not exacting. Here’s what we mean:
Before we get into the databases- let me digress for a quick
minute. We have to remember that no database will ever be perfect, just like we
are not perfect. As much as others play to our individual strengths, we have to
play to the databases strengths. It is impossible for a cost database to be
perfect or even close on material costs. Even with quarterly adjustments, the
market is simply too volatile, there is too much competition and the vendor
pool is always growing which skews material types and prices all over the
place. But cost databases do have certain strengths: equipment rental rates,
labor and productivity rates, assembly components, etc. Let’s quickly looks at
two top cost databases to expound on what I just said.
Let’s look at DCD’s cost database. We have the book;
we have logged on to the website and we have used the various components. We
have found that the DCD’s biggest strength is their historical database of
projects from across the nation. It’s pretty awesome in fact. After almost
every large job we estimate, be it a fire station or a hospital, we go to DCD
website, and use the super handy historical cost database. We choose the
building type; the core and shell construction type and it pops out a list of
similar projects. Then we go look at these projects to see what the square foot
costs are as a comparison to make sure we are not way off base.
This being said, multiple factors have to be accounted for
when doing this comparison. How long has it been since that project was built
vs the one you are estimating will be built? We add for inflation to account
for this. What materials may have skyrocketed? Lately, it’s been wood and
steel, so do we need to adjust for this? Where was the project built? We
consider not only the city and the applicable wage rate differences but also
where in the city and what type- small remote cities and large densely packed
cities can add costs when it comes to labor availability and material delivery
rates. Was this facility done for the federal government? If so, did we account
for the additional time and stressors that come with working in high security
environments? Have we accounted for current subcontractor availability?
When we go to the DCD database, it’s not a simple “oh I
found another hospital that the square footage is close enough, so mine is good
to go” process. We take a look at the closest job we can find, take the above
factors into consideration, and adjust our estimate appropriately if need be-
confirmation bias I suppose, but a well educated and thoroughly vetted bias.
So, we have found that DCD’s database can be very helpful, if used correctly
and played to it’s strengths. Its help us notice when things have been off so
in our eyes, it’s useful.
Now, let’s look at RS Means. This is a can of worms
if I’ve ever seen one. People love them or despise them. We have been using
this database for over 23 years ourselves but we use it for what we feel its
strengths are. Do we use it to price materials? We used to before pricing was
so readily available online, but now we use the material costs only for odd
things last minute. Now with the various search engines, it’s very rare that a
price cannot be found last minute for something that is accurate enough to
include in the estimate. So, what do we use RS Means for now? We have found
them to be accurate when it comes to assembly data. What items really go into a
fire sprinkler system, or a foundation footing? Did we forget to include
something? It’s a great checklist to use when building various CSI division
components of a job. We have also found them to be accurate when it comes to
crew assemblies and labor production rates. In the course of estimating we
cannot take a cost item and arbitrarily assign a “sounds good to me” labor cost
to it. We have to research production rates and crew sizes, then work backwards
to establish a per unit price for each cost item. RS means is super helpful in
doing that. You have to account for site conditions, time of year etc. and
adjust, but it gives you a great jumping off point for your own estimating. We
have a relationship with some of the top engineers over there, and their
commitment to accuracy is both impressive and reassuring. They have spent a lot
of money lately investing in updates to all aspects of their databases.
So bottom line, these databases can be trusted and used,
as long as you use them for what they are good for. A quarterback can’t win
a football game alone, but with all of their teammates, those bits and pieces
come together to form a team that can win. Same with cost databases. It would
be nearly impossible for one database to be an “end all be all” source- there
is just too much subjectivity and too much constantly changing data for that to
happen. So, using a combo of cost databases, for their respective strengths,
combined with your own historical costs and supplier/subcontractor
relationships, can help you put together a solid cost estimate. Your data is
only as good as how well you maintain and vet it in each new circumstance. Cost
databases are not the ultimate solution but rather another handy tool to have
in the estimator’s arsenal.